Planning & Execution

Project Quality Plan (PQP)

1
  • Customer requirement confirmation (schedule, specification & qualification)
  • Project team formation
  • Drawings Submission
  • Vendors Selection
  • Material & equipment selection and submission
  • Request for Information
2
  • Equipment / Material delivery inspection
  • System Installation / Construction
3
  • Installation inspection
  • Equipment / System Qualification, Testing & Commissioning (T&C)

Milestones

1

Week 1

  1. Removal of fans, false ceiling boards, shower curtains.
  2. Preparing laser marking mounting positions for tracks.
  3. Drilling of accurate mounting points.
2

Week 2

  1. Installation of down rods and lateral braces on concrete ceiling top for preparation of tracks installation.
  2. Replace, re-instate and install false ceiling board.
  3. Installation of tracks, re-instate fans, shower curtains.
  4. Checking of all tracks alignment.
  5. Ensuring electrical charging points are installed at the right places.
3

Week 3

  1. Integrate gates, turn tables with H systems.
  2. Install hoists, make good ceiling boards.
  3. Assemble moveable shower beds.
4

Week 4

 

  1. Testing of all hoists on tracks, gates, turn table and H system with the shower beds.
  2. Mock up integration of operation with Hoist system and shower beds.
  3. Professional engineers to conduct PE Structure & PE load test.
  4. First training of clients’ team. 
  5. Subsequent training to be conducted after commissioning.
  6. Official commissioning of the system.
  7. Follow up bi-monthly check in to ensure hoist and shower beds solutions are integrating well.